Measuring Property, Plant and Equipment

Property, plant and equipment starts on the balance sheet at historical cost: what it took to buy the asset, get it where it will work and make it ready to run. This lesson covers what goes into that cost, how to split a lump-sum price, when interest is capitalized, and later spending.

10 cards
Study this deck

Measuring Property, Plant and Equipment

In this lesson · 6 sections
Step 4 of 6

Capitalizing interest

Interest is part of the cost of an asset the entity builds for its own use, or builds as a one-off project to sell or lease (an office tower built to sell, for instance). It isn't capitalized for inventory produced routinely, for assets already in use, or for land that isn't being developed. For a not-for-profit, the main difference is that an asset paid for with gifts the donor restricted to buying or building it doesn't qualify, to the extent those gifts fund it; the same goes for a grant restricted that way.

The amount is the interest that could have been avoided if the spending hadn't happened:

  1. Average the accumulated expenditures for the period, weighting each payment by the time it was outstanding.
  2. Apply the rate on any borrowing taken out specifically for the project (the entity may use that rate up to the borrowing's amount).
  3. Apply the weighted-average rate on the entity's other borrowings to any excess.
  4. Capitalize no more than the interest actually incurred in the period.

Capitalization starts when expenditures have been made, construction activity is under way and interest is being incurred. It stops when the asset is substantially complete and ready for use. Interest earned by investing unspent loan proceeds is generally not netted against the amount capitalized.