Three treatments
- Separate contract. Both must hold: the scope grows by distinct goods or services, and the price rises by their standalone selling prices (adjusted for the circumstances, such as savings on selling costs for an existing customer). The original contract is left alone.
- Prospective. If it isn't a separate contract and the goods or services still to be delivered are distinct from those already delivered, the original contract is treated as terminated and a new one created. The price allocated to the remaining obligations is the consideration not yet recognized as revenue (including amounts already received) plus the consideration added by the modification. Revenue already recognized is untouched.
- Cumulative catch-up. If what remains isn't distinct, because it is part of a single obligation already partly satisfied, the new price and new measure of progress are applied as if they had always been in place, and the difference is adjusted in revenue at the modification date, up or down.
When the remaining items mix both kinds, each is handled in the way that fits the objective of these rules.
Example: a shipyard refits a ferry for 4,000,000, one obligation measured by cost-to-cost with expected costs of 3,000,000. Year 1 costs are 1,200,000 (40%), so Year 1 revenue is 1,600,000. Early in Year 2, before more work, the owner approves adding a passenger lounge built into the refit: the price rises by 600,000 and expected costs by 1,000,000.
| Amount | |
|---|---|
| New price | 4,600,000 |
| Progress: 1,200,000 / 4,000,000 | 30% |
| Cumulative revenue: 30% x 4,600,000 | 1,380,000 |
| Catch-up at the modification date | (220,000) |
Revenue falls by 220,000 even though the contract stays profitable.