Over-Time Revenue and Measuring Progress

Once an obligation qualifies for over-time recognition, the work is measuring how far along it is. This lesson tests the three over-time criteria more closely, compares output and input methods, adjusts cost-to-cost for costs that don't show progress, and recognizes losses on contracts.

10 cards
Study this deck

Over-Time Revenue and Measuring Progress

In this lesson · 5 sections
Step 2 of 5

Choosing a measure of progress

One method is used for each obligation, applied consistently to similar obligations, and progress is remeasured at every reporting date. A revised measure is a change in estimate, so the cumulative effect is recognized in the period of the change.

  • Output methods measure value delivered to the customer: milestones reached, units delivered or produced, appraisals, surveys of work done, time elapsed. Units delivered misstate progress if the customer already controls work in process that hasn't been counted.
  • Input methods measure the entity's effort: costs incurred, labor or machine hours, resources consumed, time elapsed.
  • Right to invoice: if the amount the entity can bill matches the value of its work to date, such as a fixed fee per inspection completed, it may recognize revenue equal to the amount it can invoice.

If progress can't yet be reasonably measured but the entity expects to recover its costs, it recognizes revenue equal to costs incurred until it can.