Cost-to-cost and costs that don't show progress
Under cost-to-cost, progress is costs incurred to date divided by total expected costs. Two kinds of cost are taken out of the measure:
- costs of significant inefficiency not reflected in the price, such as unexpected waste or rework, which are expensed as incurred;
- uninstalled materials: a good that isn't distinct, that the customer controls well before it is installed, whose cost is significant to the total, and that the entity buys from a supplier without significant design involvement. Its cost leaves both the measure and the price, and revenue equal to its cost is recognized when control passes (zero margin).
Example: an engineering firm integrates a production line in a customer's plant for 2,000,000, one obligation measured by cost-to-cost. Expected costs, which assumed no rework, are 1,500,000, including a 450,000 robotic welding cell bought from a robot maker with no design input from the firm. The cell isn't distinct from the integration work, and the customer controls it on delivery in Year 1; it is integrated in Year 2. Year 1 other costs are 378,000, including 42,000 of unplanned rework.
| Item | Amount |
|---|---|
| Costs that count: 378,000 - 42,000 | 336,000 |
| Expected other costs: 1,500,000 - 450,000 | 1,050,000 |
| Progress: 336,000 / 1,050,000 | 32% |
| Price excluding the cell: 2,000,000 - 450,000 | 1,550,000 |
| Revenue: 32% x 1,550,000 + 450,000 | 946,000 |
| Cost of sales: 378,000 + 450,000 | 828,000 |
| Gross profit (32% x 500,000 - 42,000) | 118,000 |