Over-Time Revenue and Measuring Progress

Once an obligation qualifies for over-time recognition, the work is measuring how far along it is. This lesson tests the three over-time criteria more closely, compares output and input methods, adjusts cost-to-cost for costs that don't show progress, and recognizes losses on contracts.

10 cards
Study this deck

Over-Time Revenue and Measuring Progress

In this lesson · 5 sections
Step 3 of 5

Cost-to-cost and costs that don't show progress

Under cost-to-cost, progress is costs incurred to date divided by total expected costs. Two kinds of cost are taken out of the measure:

  • costs of significant inefficiency not reflected in the price, such as unexpected waste or rework, which are expensed as incurred;
  • uninstalled materials: a good that isn't distinct, that the customer controls well before it is installed, whose cost is significant to the total, and that the entity buys from a supplier without significant design involvement. Its cost leaves both the measure and the price, and revenue equal to its cost is recognized when control passes (zero margin).

Example: an engineering firm integrates a production line in a customer's plant for 2,000,000, one obligation measured by cost-to-cost. Expected costs, which assumed no rework, are 1,500,000, including a 450,000 robotic welding cell bought from a robot maker with no design input from the firm. The cell isn't distinct from the integration work, and the customer controls it on delivery in Year 1; it is integrated in Year 2. Year 1 other costs are 378,000, including 42,000 of unplanned rework.

ItemAmount
Costs that count: 378,000 - 42,000336,000
Expected other costs: 1,500,000 - 450,0001,050,000
Progress: 336,000 / 1,050,00032%
Price excluding the cell: 2,000,000 - 450,0001,550,000
Revenue: 32% x 1,550,000 + 450,000946,000
Cost of sales: 378,000 + 450,000828,000
Gross profit (32% x 500,000 - 42,000)118,000