Over-Time Revenue and Measuring Progress

Once an obligation qualifies for over-time recognition, the work is measuring how far along it is. This lesson tests the three over-time criteria more closely, compares output and input methods, adjusts cost-to-cost for costs that don't show progress, and recognizes losses on contracts.

10 cards
Study this deck

Over-Time Revenue and Measuring Progress

In this lesson · 5 sections
Step 5 of 5

On the exam

Traps: a termination payment covering costs only treated as a right to payment, uninstalled materials left in the cost-to-cost ratio, rework counted as progress, and a loss recognized only in proportion to progress.

Independent exam-prep material. Not affiliated with the AICPA, NASBA, CFA Institute or CFP Board. Not financial advice. Learn more

Quiz me on this
Replacement-provider test for simultaneous consumption
Save
Enforceable right to payment for work to date
Save
Uninstalled materials under cost-to-cost
Save
Progress that can't yet be reasonably measured
Save
Anticipated loss on a construction-type contract
Save