Static and Flexible Budget Variances

A budget is a plan; the variance is how far actual results landed from it. This lesson covers labelling variances as favorable or unfavorable, why a static budget can mislead when volume changes, and how a flexible budget splits the gap into a volume effect and a price and spending effect.

7 cards
Study this deck

Static and Flexible Budget Variances

In this lesson · 5 sections
Step 2 of 5

Static and flexible budgets

A static budget is set for one planned level of activity, such as 400 events or 10,000 units. Comparing actual results with it mixes two causes: the change in volume and the change in prices and efficiency.

A flexible budget restates the budget for the actual level of activity, using the budgeted price per unit, budgeted variable cost per unit and budgeted fixed costs. It splits the static budget variance into two parts:

  • Sales-volume (activity) variance = flexible budget - static budget. It isolates the effect of selling more or fewer units at budgeted margins.
  • Flexible-budget variance = actual - flexible budget. It isolates the effect of prices, costs per unit and spending at the volume actually reached.

The two add up to the static budget variance. Fixed costs are the same in the static and flexible budgets, so any fixed-cost variance is a spending variance.

The trap a flexible budget removes: a mail-order shop budgets 120,000 of packaging for 8,000 orders. It ships 9,000 orders and spends 132,000, which looks 12,000 over the static budget. At 15 an order, the flexible budget allows 135,000, so packaging spending was actually 3,000 under (favorable).